interior
04 NOV. 2020
interior progress update
1st stage fitout
Sub breaker panel installed
Tidy plumbing under crew bathroom sink
Guest Bathroom marble
Upper deck saloon fitout continues
2nd stage carpentry in guest corridor
Main saloon 2nd stage carpentry continues
Deck head mounts being installed
2nd stage cabinetry continues in crew mess
Guest cabin
2nd stage carpentry continues
Master Shower 1st stage carpentry
Second stage carpentry
2nd stage carpentry continues
Laundry fitout continues
Deck heads in place in bridge, electrical fitout continues
Crew cabin 2nd stage carpentry continues
Guest bathroom
Guest Bathroom
Master cabin first stage fitout continues
First stage carpentry
Galley fitout continues