interior progress update

Crew Corridor - substructure complete, finish panelling in progress

Dining Room MD - Approx 25% complete

Owners Office

Lobby to Wheelhouse

Crew Cabin Fwd - Approx 60% complete

Crew Cabin Fwd - Approx 60% complete

Laundry - Main services power, water and extraction services installed. Appliances, bulkheads and decks heads to complete.jp

Laundry - Main services power, water and extraction services installed. Appliances, bulkheads and decks heads to complete

Crew Staicase

Owners Cabin - Cabinetry Appox 10% complete. Windows not yet installed

Owners Dressing Room

Captain Bathroom - Approx 60% complete

Crew Mess - Approx 40% complete

Crew Mess - Approx 40% complete

Rescue Tender Garage.jpg=

Rescue Tender Garage

LD to Laundry Stairs

Owners Lobby Cabinetry - in progress

Wheelhouse - cabinetry Approx 40% complete

Crew Bathroom - Approx 65% complete

Galley - Appliances installed, counter tops installed, floor to complete.jp

Galley - Appliances installed, counter tops installed, floor to complete