interior
15 SEPT. 2020
interior progress update
Crew Corridor - substructure complete, finish panelling in progress
Dining Room MD - Approx 25% complete
Owners Office
Lobby to Wheelhouse
Crew Cabin Fwd - Approx 60% complete
Laundry - Main services power, water and extraction services installed. Appliances, bulkheads and decks heads to complete
Crew Staicase
Owners Cabin - Cabinetry Appox 10% complete. Windows not yet installed
Owners Dressing Room
Captain Bathroom - Approx 60% complete
Crew Mess - Approx 40% complete
Rescue Tender Garage
LD to Laundry Stairs
Owners Lobby Cabinetry - in progress
Wheelhouse - cabinetry Approx 40% complete
Crew Bathroom - Approx 65% complete
Galley - Appliances installed, counter tops installed, floor to complete