engineering
15 sept. 2020
engineering progress update
Bow Thruster - Propellor not yet installed
M.E.R. AirCon Piping - in progress
M.E.R. Engine Gearbox - mounted but not aligned. Coupling to be installed
Rudder Stock
M.E.R. Engine Gearbox - mounted but not aligned. Coupling to be installed
Main Engine exhaust - loosely connected
M.E.R. Main engine exhaust filter - loosely in place
M.E.R. Main eng and Generator exhaust systems - not yet connected
Beach Club Hydraulics
Main Engine Room piping and cabling - in progress
Main Engine Room - overhead cable run
Mooring Station Fwd - hawse pipe to be finish welded