engineering

15 sept. 2020

engineering progress update

Bow Thruster - Propellor not yet installed

Bow Thruster - Propellor not yet installed

M.E.R. AirCon Piping - in progress

M.E.R. AirCon Piping - in progress

M.E.R. Engine Gearbox - mounted but not aligned. Coupling to be installed

Rudder Stock

 

M.E.R. Engine Gearbox - mounted but not aligned. Coupling to be installed

Main Engine exhaust - loosely connected

M.E.R. Main engine exhaust filter - loosely in place

M.E.R. Main eng and Generator exhaust systems - not yet connected

Beach Club Hydraulics

Main Engine Room piping and cabling - in progress

Main Engine Room - overhead cable run

Mooring Station Fwd - hawse pipe to be finish welded