PROGRESS REPORT | Q4 - 2021

These past months has seen some great progress onboard the vessel in all areas.

The 4 lower guest cabins have proceeded well with the finished walls, ceilings, and bathroom marble being installed. The first fix of the A/V systems in each cabin have been installed in the local equipment racks.

The Crew cabins and mess areas have all main furniture and cabinetry installed with small items and electronics now being installed locally.

The Galley has the main equipment installed and cupboard furniture.

The main Deck Owners cabin is progressing with the sub-structure of the walls and ceiling now installed in preparation for the finished panels to be installed in the coming weeks. The Owners bathroom is coming together well with the bathtub and large shower tray installed.

The large glass window sections on the main deck Owners cabin and salon are installed.

In the last week the Sun Deck received the large top section and is now welded in place with fairing works now able to continue on the top and sides.

The sun deck has also had the teak decks laid and protected.

Pipe work installation continues in the Engine Room connecting ancillary equipment to main cooling lines and overboard discharge.

Exterior paint has commenced in the grey undercoat for the Black topcoat areas, while the White top areas are still being finely sanded in preparation for top coat paint during the quieter Christmas break.