30 JULY 2020

engineering progress update

Rags used to protect the lagging whilst work around them continues

Replacement of insulation is required, builder has been notified.

Radio communication panel being installed

Resilient mount not connected

Electrical fit out continues, bridge breaker panel

Cable runs continue

Yacht general cleanliness is substandard. This has been addressed with the builder.

Vessel alarm display screen installed and running

AV rack installation