29 may 2020

interior progress update

Upper salon 2nd stage carpentry continues

Bridge carpentry continues

Crew stairs deck heads remaining

Owners lobby top coat paint in jet black and 2nd stage carpentry

Owners cabin fit out continues

Owners bathroom fit out continues

Captains cabin nears completion

Crew cabin nears completion

 

Upper deck pantry fit out continues

Galley nears completion

Main salon cabinetry and 2nd stage carpentry continues

Owners lobby windows top coat painted in jet black

Owners cabin fit out continues

Guest Stairs carpentry continues

Captains bathroom nears completion

Crew cabin nears completion

Operational systems board installed

Main deck Pantry nearly completed

Main salon cabinetry and 2nd stage carpentry continues

Upper deck Hallway panelling ready to be installed

Owners bathroom fit out continues

Lower Guest Cabin second stage carpentry continues

Crew mess nears completion

Crew bathroom nears completion