exterior

15 JULY 2020

exterior progress update

corrections required on black paint and sag in top coat

Wing station installed, deck to be sanded, this will remove all fouling

Deck head mock up for teak overheads

Transom door in the down position

Deck head mounts yet to be installed

Non skid painted on the bridge roof

Standing water on the metal deck, scupper has not been connected, yard will correct.

Protection on the painted surfaces

Forward rails extended on the bow area

Clearance of the door to the water

Work on the mast continues

Work on the mast continues

Glass panel in Jacuzzi yet to be installed

Seat or similar to be installed

Deckhead mounts installed

Fairing and paint work continues in the beach club area

Passeralle installed

Sun deck helm installed

Tiling completed and Jacuzzi plumbing being installed