Q3 - 2022 REPORT
INTERIOR PROGRESS UPDATE | Q3 2022
Main deck lounge
•Outfitting of these areas is continuing: piping, cabling, insulation/lagging and ducting have progressed,
• Main cable runway have now been laminated closed.
• Main engine room hatches are in place, but engines have not been installed yet, therefore they will need to come away for final main engine installation.
Master Cabin
• Insulation on walls is practically complete. We have verified in detail the boundary between the galley and the master cabin and improvements have been requested in order to minimize noise transmittal,
• Ceiling insulation is complete.
• Flooring and flooring insulation is in progress.
• Cabling is progressing fast in this area.
• Piping deck penetrations are complete.
• All windows have been installed except for the fwd STBD side one, which again will be used for embarkation of joinery.
Lower deck cabins
• Insulation / lagging is almost complete,
• Cables have been passed into these areas and awaiting connection to junction boxes which will still need to be installed.
• Ceiling raw joinery is in place.
• Bathroom areas raw joinery is in place.
• Flooring is being installed.
• The area is very close to receiving final furniture.
Upper deck - Bridge
• Insulation / lagging is close to complete,
• Deck penetrations are in progress.
• Cabling is now in place and awaiting switchboards.
• Flooring is being installed.
Upper deck - Aft UD lounge
• Insulation / lagging is close to complete,
• Deck penetrations are in progress.
• Cabling is now in place.
• Flooring is being installed.