Engineering
Q2 - 2022 REPORT
TECHNICAL PROGRESS UPDATE | Q2 2022
Engine Room
•Pins for insulation are installed throughout the engine room
•Insulation lagging is proceeding on the fwd bulkhead and is proceeding aft on the side shell
•Vibration visco-elastic plates have been bonded to external shell areas.
Engine Room
•Main engine exhaust cowlings are in place,
•Shaft line hull penetrations (stern tube) have been installed (chock fast trays ready),
•Bulkhead penetrations are in progress.
Engine Control Room
•This is the main access into the engine room areas,
•Pins for insulation are installed throughout the engine room,
•Noise suppression panels are being installed on the aft bulkhead,
•Support structure for the interior lining is now in place,
•As per the engine room, the yard has started bulkhead penetrations outfitting.
Engine Control Room
•Fluiten stern tube is located below the flooring of the control room.
Main tender Garage
•Garage areas are being gel coated at this stage,
•Piping penetrations have initiated, particularly to the fwd engine control room and engine room.
FWD Bosun locker & anchor chain locker
•These areas have not yet been accessed by the yard to initiate works. They are probably still sealed up from the transport over from Sardinia
FWD jet Ski Garage
•No progress can be viewed in these areas