02/09/2020
exterior progress update
Vessel moored port side to
Door ready for installation
Sun deck looking aft, repairs to teak caulking visable
Protection under scaffold on finished teak, caulking repairs visible
Tape applied to painted surface noted, care will need to be taken removing this without damage to the paint
Scaffold on bow to reach windows
Aft seating remains to be painted
Polishing of the pool base sole
Escape hatch yet to be installed, space protected from weather
Temporary guard rails installed, sun protection over windows
Mast installed
cable runs continue from the mast
Mast deck heads to be fitted once cable runs complete
Crane on fore deck installed
Temporary guard rails in place of glass yet to be installed.