INTERIOR progress pictures update - July 2022
The bridge deck bar is continuing to have layers of varnish applied to achieve a gloss finish.
Bridge carpentry works are almost completed, ready for the navigation equipment install that will begin in August.
Interference woodwork is being removed from a port crew cabin to allow access for replacement fire main pipework to be fabricated, painted and installed.
Crew bathrooms refreshing works are still underway. Currently under dispute with the shipyard after imperfections were found during Arrow quality control.
Aft VIP cabin woodwork removal has begun in preparation to the hot works explained on the following pages.