ENGINEERING progress pictures update - June 2022
Three Yanmar Generator engines have arrived in the shipyard along with transformers. The Electric motors have been joined together to become 2 drive motors.
Electrical switchboard controllers are also built and waiting to be delivered to the shipyard.
Navigation equipment ready to ship from supplier in France.
New Main Electrical switchboard undergoing Classification society testing.
Propellers are back from the Prop Shop, cleaned and balanced ready to be installed.
The deckhead and floor areas of the Engine Room are now cleaned and painted ready for the new equipment to begin being installed onboard.
NDT (Non-Destructive Testing) on the welds of the doubler plates of the hull repairs.
Boat Davit arms and motors have returned from service to be painted.
The new Upper Deck Bar first fitment onboard confirming location.
2nd coat of Gloss clear coat on the new bar.