Report #007 - 21 June 2022

 

Works are now progressing with speed as equipment has started to arrive in readiness for installation into the Engine Room.

  • The Upper Deck has been templated for the new teak deck to be constructed offsite in large sections for ease of installation and to allow other works to continue.

  •  The Main Mast has been painted in the new Stark White top coat color paint.

  •  Spot fairing and sanding have begun on the blue hull.

  •  The new bar was lifted onto the upper deck to confirm location and dimensions before being removed again for a clear coating of the wood.

  •  New equipment has started to arrive from suppliers. Navigation equipment from France, Generators, and transformers arrived in transport crates to then be assembled onsite by E-Motion technicians. The new electrical motors and sub-panels are in the E-Motion factory in la Spezia ready to be shipped.

  •  The Engine Room has been thoroughly cleaned in all the bilges and frames and painted in durable technical paint in readiness for the main machinery to be embarked onboard.