PROGRESS REPORT | Q3 - 2021

EXTERIOR

  • August saw the hull moved from one shed to the final finishing shed.

  • Fairing of the Upper Deck and Sun Deck continues as they have now begun to long board sand the areas for a smooth finish.

  • White primer paint is coated with the red coloured ink and sanded smooth to remove any remaining deformations in the fairing.

  • Exterior hand rails are being positioned onboard and tack welded into position for finish welding and polishing to be completed ashore.

INTERIOR

  • Lower Deck Guest cabin base installations continue with all showers having a coat of resin lining the floor and walls to water proof the area.

  • Lower Deck Guest cabin furniture has been built in the contractors workshop in readiness for installation onboard the vessel.

  • Main Deck Owners Cabin now has the walls and partitions installed and first fix plumbing in position.

  • Upper Deck Master Cabin and Bridge areas have the base layer flooring laid and electrical cables continue to be pulled.

ENGINEERING

  • Main Machinery Engine Room access hatch has now been closed as all major machinery is in place.

  • Main machinery electrical switchboard has been installed and cables are now being routed to the breaker panels.

  • The Gymnasium has now been closed off from the tender garage and is being prepared for a coat of technical paint to seal the sound deadening material.

  • The Adventure Station / Tender garage is being prepared for a sealing coat of paint on the sound deadening material.

  • Bulbous bow watertight compartment has been cleaned, prepared, and a coat of technical paint applied.

  • Pipework in the Engine room is underway with the Air Conditioning system sea water pipes.

  • Shaft bearing alignment is underway on the Port side.

 