PROGRESS REPORT | Q1 - 2022

Progress onboard continues well with the interior outfitting and paint preparation on the exterior.

This past month has been making inspections of the finished furniture in the crew area. All Cabins and the Mess have been inspected for damage and defects from the build process. This has allowed the yards contractor time to make any repairs as required.

Lower Deck Guest cabins are almost completed and will be inspected by the end of March.

The Gymnasium continues towards final fitout with cabinetry. The Kinetic weight machine has been installed onboard and the supplier will be onboard in March to set up and calibrate the system weights.

The Main Salon fit out continues with the surrounding furniture and room divider installed.

Upper Deck Owners cabin fitout continues alongside the Fortnight cabin, Captains cabin, and the Bridge.

All the glass windows have now been installed on all decks with protections on the exterior.

Technical testing has started with the Fuel and Bilge electro valve systems. This has then allowed for a small portion of fuel to be bunkered onboard for further tank calibration and testing for the fuel tank systems.

Further testing of the engineering systems will continue in the lead up to the technical launch of the vessel in April.

Main Propulsion shafts have been drawn through the hull up to the gearbox inside the Engine Room. The propellers have been installed on each of the shafts and the rudders have been installed up into their housings and connected to the steering system hydraulics.

Exterior decks are now in the process of topcoat paint being applied. These are starting with the Black areas of the superstructure and will move on to the larger white painted areas and hull.

EXTERIOR

ENGINEERING