Progress Report #10 | March 2023

Introduction

There is a decent pace going now and one can see the various changes and progression of the project.

The metal primer on the Hull is at a good stage and the filling and primer in the roof area/roll bar are impressive.

Metal works and frame installation are constant throughout the Engine room, mooring stations and beach club predominantly. 

Pipe work, insulation works, sound dampening and hot works are ongoing. There is an increased intensity in the wiring programme specifically in the Engine room.

We pay great attention to the insulation work as it will be a major factor in the Owner’s enjoyment going forward and I report it is being done correctly and with precision.

Part 2 of the welding deflection tests on the hull was carried out by San Lorenzo and witnessed by Harry Noonan, Arrow PM.

It is always nice to see the base floor going in. It is a sign of progress indeed.


HULL


IMAGES RELATE TO THE DEFLECTION TEST WHICH WAS CARRIED OUT IN TWO SESSIONS THIS MONTH


BELOW: RUBBING STRAKE REINFORCED PLATES ON TRANSOM AND HULL.

RIGHT: PRIMER COMPLETE ON 75% OF HULL AREA.


BELOW: NAIAD STABILIZER FIN SHAFT

RIGHT: MOORING WHIP INSERT HULL SIDE


HULL/TRANSOM


IMAGES RELATE TO WELDED DOOR-STOPPER/LIMITER FOR TRANSOM DOOR


MAIN DECK AFT 


STAINLESS STEEL INSERTS FOR ROPE LEADS. WELDED TO ALUMINIUM SUPERSTRUCTURE.


SUN DECK


EPI –LITE FILLER ON SUNDECK ROLL BAR BEGINS


SUN DECK CONT’D: EPI –LITE FILLER PROGRESSION CONTINUED


CUTOUTS FOR LIFE RAFTS


WHEELHOUSE/UPPER DECK


BELOW: FIRE HYDRANTS BEING INSTALLED

RIGHT: VENT GRILL FOR GMDSS BATTERIES


MOORING STATION/ANCHOR CHAIN LOCKERS


BELOW: STATION VIEWING HATCH INSTALLED

RIGHT: ANCHOR CHAINLOCKER  STRB SIDE


GALLEY


BELOW: ROCKWOOL/INSULATION AT 90%

RIGHT: EXTRACTION DUCTING IS NOW FITTED


TENDER GARAGE MAIN DECK 


BELOW: GARAGE SHELL DOOR REMOVED FOR WORKS.

RIGHT: STAIRWELL TO MOORING STATION FWD


OWNER OFFICE AREA


BELOW: EXAMPLE OF INSULATION IN PLACE

RIGHT: MARINE PLY FLOOR IN PLACE (GREY PAINT)


OWNER’S CABIN


MARINE PLY FLOOR BASE IS NOW IN POSITION AND INSULATION WORK ONGOING


BELOW: NEAT WIRING AND PIPING WORKS

RIGHT: CLEAR RESIN FLOOR IS FOR THE BATHROOM AREA. IT ACTS AS A WATER-PROOFING


MAIN DECK SALON


BELOW: FRAMEWORK FOR FLOOR IN PLACE AT BEGINNING OF MONTH

RIGHT: MARINE PLY FLOOR BASE IN PLACE IN SALON AND OWNERS CORRIDOR


 LOWER DECK GUEST BILGE AREA


TANK TOPS PAINTED IN BOLERO DEFENDER


ENGINE ROOM


BELOW: WIRING IS MOVING AHEAD WELL

RIGHT: FUEL SIGHT GLASS IN POSITION


BEACH CLUB AREA


STRB SHELL DOOR REMOVED. ANTI-HUMIDITY PAINT BEING APPLIED.


TRANSOM DOOR ON YARD FLOOR 


BELOW: VIEW OF PIN MECHANISM BEING FITTED

RIGHT: DOOR ITSELF IN LAID DOWN POSITION