Progress Report #08 | January 2023


Progress report I San Lorenzo 44m, project 157.

Location: Carrara, Italy

Report was written by Harry Noonan, Project manager at Arrow Monaco on the 31st January 2023.


Introduction

The Vessel is now blocked and in position on the Shipyard floor in the San Lorenzo production facility.

The scaffolding is almost complete in readiness for tenting. Whilst the tenting process prevails there will be much pre-outfitting works in progress which mainly includes cable tray installation throughout ,pipe work, insulation works, sound dampening  and hot-works relating to the engine room frame work.

The majority of essential  welding is already approved by both the classification society and San Lorenzo.

In fact the overall quality of the aluminium work is very good.

We now enter a very interesting/productive  phase in the Vessel’s journey.


VESSEL IN POSITION AT SAN LORENZO FACILITY


EARLY STAGES OF SCAFFOLDING DEC 2022


SCAFFOLDING AT ADVANCED STAGE MID JAN 2023


MAINDECK


MAIN DECK PORT AND STBD SIDE WALK WAYS VIEW FROM AFT


MAINDECK AFT


IMAGE BELOW SHOWS STAIRWELL TO SWIMMING PLATFORM FROM AFT DECK.

IMAGE ON THE RIGHT: MOORING STATION BASE.


FOREDECK


IMAGE BELOW IS VIEW FROM WHEELHOUSE.

IMAGE ON THE RIGHT: VIEW FROM OWNER VIEWING LOUNGE.


IMAGE BELOW IS JACUZZI FRAME FACING AFT.

IMAGE ON THE RIGHT: VIEW FROM THE BOW.


MAIN SWITCHBOARD COMMISSIONED


MAIN SWITCH WAS COMMISSIONED AND WITNESSWD BY SL, ABS AND ARROW SURVEYOR AT THE FACTORY.

EXCELLENT QUALITY.

 

ENGINE ROOM


BELOW IS FRAMEWORK FOR MAIN SWITCHBOARD.

IMAGES ON THE RIGHT: TANK TOPS AND FRAMEWORK IN THE ENGINE ROOM BILGE AREA.

 

BELOW IS AN IMAGE OF THE SEACHEST BUTTERFLY VALVE AND CATHELCO VALVES.

IMAGE ON THE RIGHT: MANHOLE ENTRY TO FUEL OIL TANK ER.


LOWER DECK GUEST AREA


BELOW IS AN IMAGE OF THE EMERGENCY BILGE PIPES IN INOX.

IMAGES ON THE RIGHT: EXAMPLES OF FRESH WATER PIPING.


MAIN SALON


BELOW IS A VIEW OF MAIN SALON FROM AFT – ITS VERY EARLY IN ITS JOURNEY.

RIGHT: EARLY STAGES OF SOUND DAMPENING PROCEDURE.


OWNER VIEWING LOUNGE AREA


THE WORKS IN PROGRESS ARE MAINLY TOPGRADE SOUND INSULATION FINISHED WITH MAPFLEX AND MUCH AIR-CON DUCTING IN EVIDENCE.

 

BEACH CLUB AREA


IMAGE BELOW WE HAVE THE BEACH CLUB FROM AFT.

IMAGE ON THE RIGHT: THE RUDDER STOCK PORT SIDE.