engineering
31st august 2020
engineering progress update
Technical locker port main deck- cladding complete
After tech space- garage bilge system upgrade in progress
Forward tech space- bilges cleaned and ready for deck plate installation
Main engine- gearbox coupling alignment checks following SL seatrial
Fuel oil flow meter installed for sea trials
Forward tech space- pre commissioning checks in progress
Rescue tender garage forward- cleaned and cladding almost complete