EXTERIOR

8th may 2020

progress update

Sundeck glass on aft installed, primer paint applied

Sundeck glass on aft installed, primer paint applied

Upper deck brown paper covers final paint

Upper deck brown paper covers final paint

Bridge deck primer paint

Bridge deck primer paint

Owners deck primer paint

Owners deck primer paint

Main deck windows + doors installed

Main deck windows + doors installed

Main deck mooring equipment installed

Main deck mooring equipment installed

Hull transom and swim platform

Hull transom and swim platform

Underwater line bowthruster ready for install

Underwater line bowthruster ready for install

 

Sundeck deckhead support mounts

Sundeck deckhead support mounts

Upper deck paint prep continues

Upper deck paint prep continues

Bridge deck primer paint

Bridge deck primer paint

Owners deck primer paint

Owners deck primer paint

Main deck paint preparation continues

Main deck paint preparation continues

Main deck paint preparation continues

Main deck paint preparation continues

Hull primer applied

Hull primer applied

Sundeck forward pilot station adjustable stanchions

Sundeck forward pilot station adjustable stanchions

Upper deck glass installed

Upper deck glass installed

Bridge deck primer paint

Bridge deck primer paint

Owners deck primer paint

Owners deck primer paint

Main deck preparation of cap rail mounting

Main deck preparation of cap rail mounting

Main deck doors installed

Main deck doors installed

Hull primer applied to bow

Hull primer applied to bow