EXTERIOR
8th may 2020
progress update
Sundeck glass on aft installed, primer paint applied
Upper deck brown paper covers final paint
Bridge deck primer paint
Owners deck primer paint
Main deck windows + doors installed
Main deck mooring equipment installed
Hull transom and swim platform
Underwater line bowthruster ready for install
Sundeck deckhead support mounts
Upper deck paint prep continues
Bridge deck primer paint
Owners deck primer paint
Main deck paint preparation continues
Main deck paint preparation continues
Hull primer applied
Sundeck forward pilot station adjustable stanchions
Upper deck glass installed
Bridge deck primer paint
Owners deck primer paint
Main deck preparation of cap rail mounting
Main deck doors installed
Hull primer applied to bow