Progress Report #01 | Q1 2023 | Kick-Off
30/03/2023
Below is a series of images relating to the works in progress on the Mangusta 104 hull no. 6.
Arrow representatives, Technical Manager Matthew Wood and Project Manager Harry Noonan were present at Mangusta facility in Viareggio for the purpose of surveying the Vessel on site and also carrying out a very productive “Kick-off meeting” with the Mangusta Technical team and project management.
We discussed outstanding items of the specifications sheet in great detail including but not limited to the paint scheme, handrails, options list, USB sockets and the Star link concept.
We are all looking forward to working in harmony to build and deliver this wonderfully designed Performance Yacht.
An on-site survey was also conducted and these images relate to the progress at this time. As she is at an early stage in the adventure we are studying the FRP practice and results. There is good evidence of correct overlapping of fibre glass matting throughout as well as reinforcement on deck joints with approved bonding/sealing joints.
The Mangusta team are happy with the schedule so far ,which bodes well for our project.
STERN – BELOW WATERLINE
CALIBRATION AND PLACEMENT OF STEEL GASKETSFOR THE KAMEWA JET “ NOZZLES”
STERN – BELOW WATERLINE CONT’D
EARLY STAGES OF EXHAUST OUTLETS.
STERN/TRANSOM
BELOW: FAIRING AND FILLING ON CLEAT BASE.
RIGHT: TENDER GARAGE AND SWIMMING WITH STAIRWAY LEADING TO AFT DECK.
MAIN SALON
BELOW: FRP SYLIGHT IN IT’S INFANCY.
RIGHT: MAIN SALON AS VIEWED FROM AFT.
MAIN SALON CONT’D
BELOW: AS VIEWED FORM FORWARD.
RIGHT: PORT SIDE DECK WALKWAY.
WHEELHOUSE
AT THIS STAGE IT IS RAW FRP FRAMEWORK.
FOREDECK
BELOW : STORAGE CUPBOARD STRB SIDE.
RIGHT : VIEW FROM THE BOW.
ENGINE ROOM
REINFORCED FRP FOR EXHAUST SYSTEM.
BELOW: FRAMEWORK INSTALLATIONS.
RIGHT: SEA CHEST INSERTS.
BILGE AREA FORWARD
BELOW: BOW THRUSTER FRAMEWORK INSIDE .
RIGHT: FW PIPING IN FORWARD BILGE.
VIP CABIN /GUEST AREA CONT’D
BELOW: CABLE TRAY FLANGE PENETRATION.
RIGHT: EXAMPLE OF THROUGH HULL FITTING.
VIP CABIN /GUEST AREA
BELOW DECKS IS AT A VERY EARLY STAGE OF BILGE PIPE INSTALLATION / WIRE TRAY INSERTION AND CONT’D FRP WORKS.