Progress Report #09 | Q2 2023

MAY 2023

Arrow Monaco has been engaged to review the status and quality of the build of the new build Mangusta 104 hull number 5.

The outfitting is taking place at the Mangusta facilities in Viareggio.

The finished vessel will have the following arrangement:

And the following specifications:

CONSTRUCTION

HULL: SINGLESKIN COMPOSITE

SUPERSTRUCTURE: SANDWICH COMPOSITE

DIMENSIONS

LENGTH OVERALL: 31.80 M / 104'3''

BEAM: ~ 7.1 M / 23'3''

MAX DRAFT: ~ 1.5 M / 4'11''

DISPLACEMENT AT FULL LOAD: ~ 120 T / 264,560 LBS

DISPLACEMENT AT HALF LOAD: ~ 110 T / 242,500 LBS

GROSS TONNAGE: < 200 GT

TANK CAPACITY

FUEL CAPACITY: ~ 10,500 L / 2,770 US GALS

WATER CAPACITY: ~ 1,600 L / 425 US GALS

PROPULSION

MAIN ENGINES:   2 x MTU 16V 2000 M96L 2600 HP @ 2450 RPM

TRANSMISSION:   2 x WATERJETS KAMEWA S63-4

STABILIZERS:   ZERO SPEED AND UNDERWAY

PERFORMANCE

MAX SPEED HALF LOAD:   ~ 35 KNOTS

CRUISING SPEED HALF LOAD:   ~ 25 KNOTS

RANGE AT CRUISING SPEED:   ~ 370 NM

ACCOMMODATION

GUESTS:   UP TO 10 IN 4 CABINS

CREW:   4 IN 2 CABINS

DESIGNER

EXTERIORS:   LOBANOV DESIGN / OVERMARINE GROUP

INTERIORS:   LOBANOV DESIGN / OVERMARINE GROUP


INTRODUCTION

Arrow representatives, Technical Manager Matthew Wood, and Project Manager Harry Noonan were present at the Mangusta facility in Viareggio for the purpose of surveying the Vessel.

The points below give a clear and concise description of progress at this stage of the build.

  • Port jet drive has been removed for a service recall.

  • Technical filler to be applied around the exhaust and bow thruster in early June.

  • The Tender garage structure has been installed.

  • All main machinery, central island, and pumps have been installed apart from the gyro stabilizer that will be installed via the soft patch in the tender garage.

  • Main deck salon parquet laying preparations are underway and the exterior teak is almost complete.

  • Interior fit-out continues at a good pace.

  • Fixed curved deckhead panels in the accommodation have been installed

  • Beds and Pullman are being fitted and shaped.

  • Bridge electronics and console progress.

  • Fan coil installation is ongoing throughout the accommodation and laundry extraction is installed.

  • Galley fridges and appliance installation are underway.


STERN – BELOW WATERLINE


Below: Kamewa “ starboard nozzle”  in place. The Port nozzle was removed for service recall.


Below: Kamewa impellor shaft and impellor are now in position on the starboard side.

Right: View of water intake under the hull.


GARAGE / GARAGE DOOR


Below: Tender crane base in position.

Right: Garage door hydraulics being pressure tested.

 

TENDER GARAGE


Below: Tender Garage access hatch.

Right: Garage door unit/frame in final position. Early stages – much work ahead.


ENGINE ROOM (“ER”)


Engine room systems and critical equipment are being installed constantly at this time.

 

Fresh water pumps in position.


ER insulation is coming along nicely.


FOREDECK


Teak laying is at 100% on the foredeck.


MAIN SALON


Below: View from aft deck-continuous progress in the fitting.

Right: The entrance, the sliding door is operable and well-protected.


MAIN SALON SKYLIGHT



FLYBRIDGE


Example of top coating on the flybridge and radar arch.


WHEELHOUSE


 The framework around the windscreen and consul is in progress.


WHEELHOUSE CONSUL TECHSPACE


24V DC electronic boxes for navigation and power continue to be installed.


GALLEY / CREW AREA


Home appliances, fridges, fan coils, and ceilings fitted.


LOWER DECK OWNER / VIP / GUEST CABINS


Joinery and bathroom fitting are ongoing and coming along well.




Below: Fan coil units installed.

Right: Italy’s Happiest Carpenter!!