Progress Report #07 | Q1 2023
MARCH 2023
Arrow Monaco has been engaged to review the status and quality of build of the new build Mangusta 104 hull number 5.
The outfitting is taking place at the Mangusta facilities in Viareggio.
The following report illustrates the status of the build as of the 16th March 2023 when the vessel was visited.
The finished vessel will have the following arrangement:
And the following specifications:
CONSTRUCTION
HULL: SINGLESKIN COMPOSITE
SUPERSTRUCTURE: SANDWICH COMPOSITE
DIMENSIONS
LENGTH OVERALL: 31.80 M / 104'3''
BEAM: ~ 7.1 M / 23'3''
MAX DRAFT: ~ 1.5 M / 4'11''
DISPLACEMENT AT FULL LOAD: ~ 120 T / 264,560 LBS
DISPLACEMENT AT HALF LOAD: ~ 110 T / 242,500 LBS
GROSS TONNAGE: < 200 GT
TANK CAPACITY
FUEL CAPACITY: ~ 10,500 L / 2,770 US GALS
WATER CAPACITY: ~ 1,600 L / 425 US GALS
PROPULSION
MAIN ENGINES: 2 x MTU 16V 2000 M96L 2600 HP @ 2450 RPM
TRANSMISSION: 2 x WATERJETS KAMEWA S63-4
STABILIZERS: ZERO SPEED AND UNDERWAY
PERFORMANCE
MAX SPEED HALF LOAD: ~ 35 KNOTS
CRUISING SPEED HALF LOAD: ~ 25 KNOTS
RANGE AT CRUISING SPEED: ~ 370 NM
ACCOMMODATION
GUESTS: UP TO 10 IN 4 CABINS
CREW: 4 IN 2 CABINS
DESIGNER
EXTERIORS: LOBANOV DESIGN / OVERMARINE GROUP
INTERIORS: LOBANOV DESIGN / OVERMARINE GROUP
INTRODUCTION
Attached is a series of images relating to the works in progress on the Vessel.
Visits were carried out by Arrow at Mangusta facility: Harry Noonan Project Manager. This report leans heavily towards joinery and woodwork as that is a prime objective at this stage.
• The Wiring programme is ongoing and making progress aft , Wiring is at 100% forward VIP.
• Fairing work on the exterior is ongoing and the flybridge is now accessible.
• Teak caulking and initial sanding has commenced forward area of bridge.
• Teak has been freshly laid on the fly bridge this week.
• Plumbing pipework is continuous at this stage and is now at around 50 % in lower deck area.
• Main Engine pre-alignment works are ongoing and the stainless exhaust piping is being calibrated .
• Boss cabin and guest cabins have progress in joinery items and one can clearly see the finished door frames in places.
• We had a milestone this week regarding carpentry and I had a visit to the workshop to see finishing items including furniture for the entire crew mess and guest bathrooms.
• I am confident that the finish will be excellent. My previous experience of Mangusta leads to have a culture of very decent woodwork from their team. It has been the same team for over twenty years.
STERN – BELOW WATERLINE
Below: Kamewa “ nozzles” in final position after calibration.
Right: Humphree’s interceptors installed on Hull.
HULL
Hull fairing work ongoing on all forward areas.
TENDER GARAGE
Tender garage is at a relatively early stage of development.
ENGINE ROOM
Extensive stainless welding achieved on Main engine exhaust pipe network. Once calibrated all will be removed for finishing and polishing.
FOREDECK
Below: Stainless base inserts for windlass and cleats.
Right: Continued fairing detail on lockers forward.
BOW THRUSTER
Below: Bow thruster motor in position below decks with protective cover.
Right: Bow thruster bracket/shaft in position. Note there is further Fibre glass work ongoing.
MAIN SALON
Below: Side window panes in position.
Right: Sikaflex work around glass is well applied.
FLYBRIDGE
Freshly laid teak on Flybridge.
GALLEY
Below: Measurements in evidence for eventual Galley equipment installation.
Right: Main services switchboard being worked on.
CAPTAIN CABIN
Bathroom fittings /shower base coming together
VIP CABIN / GUEST AREA
Below: paint work finished above deckhead panels in preparation for deck head panels.
Right: Excellent pipework installation.
VIP CABIN / GUEST AREA
Below: Junction boxes and electrical work in progress.
Right : Pipework through interior walls in final position.
GALLEY / CREW AREA
Door frames finished, protected and in position.
CARPENTRY WOOD SHOP VISIT
Below: Bathroom mirror frames in foreground
Right: Numerous carpentry items awaiting final installation.
CARPENTRY WOOD SHOP VISIT
Below: Protected frames and cabinets for interior .
Right: Entire bridge framework awaiting paintworks and eventual finishing at a later date.