Progress Report #06 | Q1 2023

FEBRUARY 2023

Arrow Monaco has been engaged to review the status and quality of build of the new build Mangusta 104 hull number 5.

The outfitting is taking place at the Mangusta facilities in Viareggio.

The following report illustrates the status of the build as of the 28th February when the vessel was visited.

The finished vessel will have the following arrangement:

And the following specifications:

CONSTRUCTION

HULL: SINGLESKIN COMPOSITE

SUPERSTRUCTURE: SANDWICH COMPOSITE

DIMENSIONS

LENGTH OVERALL: 31.80 M / 104'3''

BEAM: ~ 7.1 M / 23'3''

MAX DRAFT: ~ 1.5 M / 4'11''

DISPLACEMENT AT FULL LOAD: ~ 120 T / 264,560 LBS

DISPLACEMENT AT HALF LOAD: ~ 110 T / 242,500 LBS

GROSS TONNAGE: < 200 GT

TANK CAPACITY

FUEL CAPACITY: ~ 10,500 L / 2,770 US GALS

WATER CAPACITY: ~ 1,600 L / 425 US GALS

PROPULSION

MAIN ENGINES:   2 x MTU 16V 2000 M96L 2600 HP @ 2450 RPM

TRANSMISSION:   2 x WATERJETS KAMEWA S63-4

STABILIZERS:   ZERO SPEED AND UNDERWAY

PERFORMANCE

MAX SPEED HALF LOAD:   ~ 35 KNOTS

CRUISING SPEED HALF LOAD:   ~ 25 KNOTS

RANGE AT CRUISING SPEED:   ~ 370 NM

ACCOMMODATION

GUESTS:   UP TO 10 IN 4 CABINS

CREW:   4 IN 2 CABINS

DESIGNER

EXTERIORS:   LOBANOV DESIGN / OVERMARINE GROUP

INTERIORS:   LOBANOV DESIGN / OVERMARINE GROUP


INTRODUCTION

 

Attached is a series of images relating to the works in progress on the Vessel.

 Visits were carried out by Arrow at Mangusta facility: Harry Noonan and Matthew Wood.

• The Wiring is ongoing but actually 100% in place in forward guest areas.

• Fairing work on the exterior is ongoing as well as evidence of first coats of topcoat –this is an excellent development and this first coat is not only a filler coat but is used to sand back and iron out imperfections-The chosen Hull colour looks great.

• The teak on the main deck is laid.

• Plumbing pipework is continuous at this stage.

• Main engines in place for pre-alignment. They will be removed for further fitting and framework in 2 weeks’ time and put back in place permanently in May 2023.

• Guest areas and Boss cabins are joineries orientated. It is pre-joinery at this stage so we await images of real progress over the following weeks.


STERN - BELOW THE WATER LINE

Below: Stainless plates bonded on hull in preparation for installation of Kamewa “ nozzles”

Right: Humphree’s interceptor plate 1


STERN

Kamewa Nozzles now in place.


STERN AREA

Below: example of under water lights installation.

Right: Top coat applied-this is an early coat which gives a nice image of what the overall finish of the port quarter will eventually look like.


HULL

Below : Moulded recess for mooring cleat. Upgrade requested free of charge for a more robust load bearing spec. It will look exactly like original spec.

Right : Galley extraction duct on Starboard side-not finished.


TENDER GARAGE

Below : View from swimming platform. Garage is in very early stages of construction.

Right :  Moulded wall which protrudes into ER which enables the Williams tender launch-clever design.


TENDER GARAGE CONTINUED

Below: View of tender garage/ER partition bulkhead.

Note: robust  FRP application and correct insulation.

Right: view from ER.


ENGINE ROOM

GRP casing ER ventilation port side


ENGINE ROOM CONTINUED

Main engines in place for pre-alignment of hydraulics, exhaust  and shaft alignment

Main engines will be removed again in 2 weeks and put in final position at the end of May.


FOREDECK

Below: Teak work  on foredeck and side deck.

Right  below: teak thickness measured at 12mm.


FOREDECK CONTINUED

Below: Teal work laid, caulked and protected until final sanding.

Right: fore deck lockers –hinged lockers requested free of charge.


VIP CABINS / GUEST AREA

Below: Wiring finished above deckhead panels

Right: Escape hatch VIP


PIPE WORK THROUGH BEAMS

Images show pipework practices we are monitoring. We are in constant discussion with yard regarding quality of installation.


GALLEY / CREW AREA

Joinery and wiring continuous in lower deck.