Progress Report #04 | Q2 2023

•The Boat is going to be delayed leaving Turkey, which has left getting a lot more done, such as the insulation and sound plates installed. 

•We noticed the boat was a clean environment compared to  596 and you could tell straight away the steelwork was a lot cleaner with less grinding and less amounts of small individual plates. 

•Dry wall going up in the crew areas was nearly completed

•We have made it very clear with the amount of insulation being installed, is to make sure the boat is completely sealed so no seawater or rain can damage the insulation during delivery. 

•There are some noticeable differences between 596 - 598 one being that the stanchion base pots are installed on 598 but not on 596, during our next PGM we would like to see how the stanchions will be fitted on 596.

•The keel compartments. looking through the keel plugs you could see inside was very dirty with iron filings and other waste. Also, a large brush was noted to be in the aft part of the skeg. These areas should have been inspected before the keel was welded to the hull. 


PORT HULL LOOKING FWD

MUD ROOM AND BEACH CLUB BALCONIES

PORT TENDER DOOR


PORT BOW SECTION

MAIN MAST SECTION INSTALLED IN ITALY

BOW

STB BOW

BEACH CLUB BALCONY LD 101

STB AFT UNDERBELLY

STERN

STERN DOOR

BEACH CLUB BALCONY LD 101


ECR LD 110 - SOUND PLATES ADDED ON FWD BULKHEAD

LOWER ENGINE ROOM LOOKING AFT

CREW MESS LD 115

LOWER ENGINE ROOM SOUND PLATES ADDED TO THE HULL

BOW THRUSTER ROOM ULD 11

LOWER ENGINE ROOM SOUND PLATES ADDED TO THE HULL


AFT ENGINE ROOM STB SHAFT TUNNEL

PUMP ROOM ULS 01 LOOKING FWD

CREW CABIN LD 121

CREW CABIN LD 123

PORT SIDE TENDER GARAGE MD 226

TECHNICAL ROOM LD 144

RACK ROOM LD 143


TENDER GARAGE MD 226 LOOKING AFT

GUEST CABIN VIP PORT MD 221

MOORING DECK MD 227

MOORING DECK MD 227

GUEST CABIN MD 212

GUEST LOBBY MD 206

GUEST CORRIDOR MD 209


GUEST LOBBY DAY HEAD MD 205

STANCHION POTS

FWD SUN DECK


MOVING PROCESS