Progress Report #03 | Q1 2023
January visit
•598 is currently in hull and superstructure construction phase in Pina Marin Shipyard, Istanbul area, Turkey.
•This report shows the current status of 598 for the month of January 2023.
•Preparation for insulation taking place Owners Deck
•Welding work continuing on Main Deck
•Lower Deck forward interior section primer application taking place on week 3 inspection
•Upper Lower Deck forward part sandblasting to take place week 4
•598 will have the finished profile shown below on completion.
Port & Starboard side hull remain the same as December 2022 with the primer application completed
SUN DECK LOOKING AFT WITH POOL CONSTRUCTION ON GOING
BRIDGE DECK LOOKING FORWARD
BRIDGE DECK TO HELI DECK
BRIDGE DECK LOOKING TO OWNERS DECK POOL CONTRUCTION
OWNERS STATE ROOM LOOKING FORWARD
OWNER SALON LOOKING AFT TO POOL
POOL CONSTRUCTION OWNERS DECK
POOL AREA OWNERS DECK LOOKING FORWARD
MAIN DECK GUEST CABIN PARTIONED
MAIN DECK EXTERIOR PASSAGE LOOKING AFT
LD MUDROOM DOOR INSTALATION PREPARATION
ULD PORT MAIN ENGINE FOUNDATION AND STERNTUBE
ULD LOOKING FORWARD TO BOW THRUSTER SPACE
SWIM PLATFORM LOOKING FORWARD
ALUMINIUM MAST CONSTRUCTION STARTED