Progress Report #01 | Q2 2022


Progress report on metal works on P598, Admiral.

Location: Yalova, Turkey

Report compiled by Noel Walsh, Technical Director at Arrow Monaco 24/06/2022.


The hull structure is 90% complete, progress shown in photos below of the bow section progress.


The bow thruster tunnel is installed below.

The right photo shows the anchor windlass platform installed.  


Below, is the main deck looking forward.

Right, main deck looking AFT.


Below, Hull looking Forward STBD side.

Right, Hull looking Forward Port Side.


The stabilizer substructure is now installed. Hull opening will be completed at a later stage. 


Right, Tank outfitting ongoing, manholes installed.

Below, hull rub rails ongoing.


Below, Watertight sliding door installed on Lower Deck.

Right, Block erection ongoing, superstructure to commence in coming weeks.