Progress Report #01 | Q2 2022
Progress report on metal works on P596, Admiral.
Location: Yalova, Turkey
Report compiled by Noel Walsh, Technical Director at Arrow Monaco 24/06/2022.
The hull structure has had steel work repairs carried out and is waiting for a new coat of primer.
All hot works on the hull are completed.
The Engine Room outfitting is ongoing. Highlighted steel defects are now all repaired. Insulation pins are installed in ER.
Generator mounts are now completed.
The Sub floor steelwork has begun in crew areas.
Hull doors fitted.
Tank inspections are ongoing, including pressure testing and water testing.
Tank outfitting is ongoing.
The Superstructure outfitting ongoing. Glands and penetrations are fitted in various locations.
Sun deck looking Forward and looking Aft. Exterior outfitting/alloy structure starting to be installed.