Progress Report #08 | 14th July 2022
Exterior paint works on the superstructure and decks are well underway, and equipment is arriving and being prepared for embarkation to the engine room.
Paintworks are completed as follows in stark white: Pilot house and bulwarks, inboards on the bow, sundeck.
Hull paint preparation is underway.
The upper deck teak is almost completed off-site and will shortly be delivered to the shipyard for installation, the decks are now ready to receive the teak.
New engine room equipment is continuing to arrive on site, components are being assembled and ready for engine room embarkation accordingly. Electric propulsion motors, gearboxes, and diesel generators.
Main switchboard has been embarked and secured and the electrical team is busy with cable preparations.
Stabilizer actuators and motors are installed. Deck machinery service and paint works are underway.
Original pumps and pipework are being reinstalled and freshly serviced.
Welding works are continuing and tested as per classification regulations.
Upper deck bar is back in the workshop to continue finishing works.
Paint works
Teak Decks
Engine room and swtitchboard
Engineering equipment embarkation preparation, electric propulsion motors, transformers and generators.
Continuation of welding works and testing in preparation for paint.
Engineering general
Upper deck bar