ENGINEERING progress pictures update

Black Water tank refurbishment works in progress

Bilge descaling works cleared away years of flaking rust back to clean steel but also reveals areas in need of repair

 

Bilge descaling works cleared away years of flaking rust back to clean steel but also reveals areas in need of repair

Hull plate removal of previous stabiliser unit in readiness for insertion of new spider frame stabiliser fin system

New Stabiliser hull plate and spider framework in construction at the welding facility

Both original Propellers at the prop shop for cleaning, gauging, and balancing

Black Water tank refurbishment works in progress

Bilge descaling works cleared away years of flaking rust back to clean steel but also reveals areas in need of repair

Previous Stbd & Port Stabiliser system hull mounting arrangements

Stbd side hull where the new stabiliser section will be installed and the hull opening for main machinery can be seen

 

Both original Propellers at the prop shop for cleaning, gauging, and balancing

Bilge descaling works cleared away years of flaking rust back to clean steel but also reveals areas in need of repair

Bilge descaling works cleared away years of flaking rust back to clean steel but also reveals areas in need of repair

Previous Stbd & Port Stabiliser system hull mounting arrangements

New Stabiliser hull plate and spider framework in construction at the welding facility

 