EXTERIOR

February 2022

Exterior progress picture update

Upper Deck teak removal complete to bare steel

Swim platform ground back to clean steel and exposing areas of corrosion to be treated

Repairs to fairing blisters on the bridge deck house and bulwarks

All portholes cleaned back to steel exposing areas of underlying corrosion that will be treated prior to new coatings

 

Upper Deck teak removal complete to bare steel

Swim platform ground back to clean steel and exposing areas of corrosion to be treated

Repairs to fairing blisters on the bridge deck house and bulwarks

All portholes cleaned back to steel exposing areas of underlying corrosion that will be treated prior to new coatings

Upper Deck teak removal complete to bare steel

Repairs to fairing blisters on the bridge deck house and bulwarks