engineering
07 jan. 21
engineering progress update
Tender Garage Bilge Water Tank in Progress
Main Engine Alignment in Progress
Main Engine Control Panel Installation Complete
Fwd Tech Space piping in progress
Main Engine Fule Filter Installation in Progress
Main Switchboard Installation almost complete
Stern Tube Bearing Installation Complete
Generator and Main Engine Exhaust System in Progress
Grey Water System Commissioning In Progress
Hot Water Tank Installation Complete
Main Switchboard
Engine Room Tank Tops
Fuel System Piping Complete
Main Engine and Generator Engine - Battery Charger Installation Complete
Reverse Osmosis System - Installation in Progress
Main Engine Room Insulation Installation in Progress