Progress Report #02 | March 2023
Introduction
•Project 606 is currently in hull and superstructure construction phase in AES Shipyard, Istanbul area, Turkey.
•Construction has started on the aluminium superstructure this month.
•This report shows the current status of 606 for the month of March 2023.
•606 will have the finished profile shown below on completion.
•BL03,BL04 & BL05 are in the connection stage.
•BL02,PC03,PC04 & BL06 are in the block construction stage.
•Aluminium block construction has started with SA01,SA02,SA03. They are under block construction.
•Block drawing below for reference.
BLOCK CONSTRUCTION & CONECTION LEFT TO RIGHT BL05,PC04,PC03,BL02
BL05,BL04,BL03 PORT SIDE
BL03 AFT
LEFT TO RIGHT BL05,BL03 LOOKING FORWARD, BL03 LOOKING AFT
BLOCK CONSTRUCTION PC04
BLOCK CONSTRUCTION BL02
BLOCK CONSTRUCTION BL06. ALUMINIUM CONSTRUCTION SA03,SA02