Progress Report #03 | January 2023
Introduction
•604 is currently in hull and superstructure construction phase over two sites in Orhanlı and Tavasanli, Istanbul area Turkey.
•Orhanli is where the block construction phase of 604 is taking place as shown in the December report. Tavasanli has started on the erection of prefabricated blocks. The blocks will be continued to be transported to Tavasanli for as they are completed.
•This report shows the current status of 604 for the month of January 2023 from both above locations with reference to the construction block drawing.
•The following shows block production taking place in Orhanlı.
•Clockwise from front left of the drawing the following blocks are in construction numbers referenced from the below drawing.
•BT02,CI02,PC05,PC02,PC04,PC03,BT08,BT07,C107,BT03,CI03.
BLOCK PRODUCTION
BLOCK PRODUCTION BT03,CI03 & Main Engine Foundation
BLOCK PRODUCTION BT03
BLOCK PRODUCTION PC03
BLOCK PRODUCTION PC04BLOCK PRODUCTION PC04
BLOCK ERECTION OF BLOCKS SHOWN FROM BLOCK DRAWING EXTRACT
BLOCK ERECTION BT04, AUXILARY ENGINE ROOM,C104 LOOKING FORWARD
BLOCK ERECTION CI04 TENDER GARAGE DECK LOOKING AFT
BLOCK ERECTION STABILISER SPACE CI05 & CI06